Skip to content
Robotlar

BMR Takipli Beton Dağıtım Bomu 12-20 m

Intelligent Follow-Up Concrete Placing Boom

Placing radius
12 / 15 / 18 / 20 m
HG12 / HG15 / HG18 / HG20
Total weight
1.6 / 1.7 / 3.1 / 3.3 t
Excluding counterweight
Wind resistance
13.8 m/s
Force 6 wind

The BMR Intelligent Follow-Up Concrete Placing Boom is a construction machine that places concrete on floor slabs and in basements at a 12, 15, 18 or 20 metre radius, managing the boom movements by algorithm.

Read more

In follow-up mode a single-person hand controller needs 30 percent of the traditional labour; in automatic mode it places along a preset route by itself and cuts spreading work by 13 percent. It switches between four modes, automatic, follow-up, jog and manual, runs on 380 V three-phase power and withstands 13.8 m/s wind.

Enterprise supply · specification support · integration engineering

Overview

The Follow-Up Concrete Placing Boom mechanises the distribution of slab concrete over the formwork and comes in four sizes by placing radius: 12, 15, 18 and 20 metres. Machine weight excluding counterweight is 1.6 t at 12 m, 1.7 t at 15 m, 3.1 t at 18 m and 3.3 t at 20 m; the minimum weight for floor-to-floor transfer is 1.6-1.7 t (2.2 t) at 12 and 15 m, 2.2 t at 18 m and 2.5 t at 20 m. The 12 and 15 m editions sit on the slab with 3.6 × 3.6 and 4.2 × 4.2 m outrigger spans; the 18 and 20 m editions are installed in a reserved slab opening of 1.2 × 1.2 to 1.5 × 1.5 m or in a lift shaft of 2.1 × 2.1 to 2.3 × 2.3 m.

There are four operating modes: automatic mode placing along a preset route by itself, follow-up mode run by one person with a hand controller, jog mode where the main and fly booms are driven by remote control, and traditional manual pulling; placing continues whatever the conditions. Follow-up placing saves two placing workers and automatic placing one more levelling worker; the high uniformity of automatic placing cuts spreading work by 13 percent, and together with a high-precision slab the slab cost falls by about 28 percent. The machine is operated directly by traditional workers; automatic slab placing needs no BIM data. Ten safety designs raise the safety of the placing process; the whole structure has passed simulation and field testing, with a main structure life above 3 years. Working voltage is three-phase five-wire AC 380 V (±40 V) and maximum wind resistance 13.8 m/s (force 6). References: at the Shenzhen Semiconductor and Advanced Manufacturing Industrial Park (278,000 m², China Construction Third Engineering Bureau) the follow-up boom worked in step with the 2.5 m levelling robot, one operator managed placing and the workforce fell by 4 people (40 percent); at the Asia-Pacific Headquarters of CanSino Clinical Research in Guangzhou (47,988 m²) the same set cut the workforce by 40 percent; Foshan Fengtong Garden, one of the first intelligent-construction pilot projects of China's Ministry of Housing and Urban-Rural Development, was built with more than 20 construction robots.

Key Advantages

A boom that follows the operator

In follow-up mode the main and fly booms are managed by algorithm; one person drives the placing with a hand controller and 30 percent of the traditional labour suffices.

  • Two placing workers are saved.
BMR Takipli Beton Dağıtım Bomu 12-20 m, A boom that follows the operator

Automatic placing, 13 percent less spreading

In automatic mode the boom places along a preset route by itself; high uniformity cuts spreading work by 13 percent and frees one more levelling worker.

  • No BIM data is needed.
BMR Takipli Beton Dağıtım Bomu 12-20 m, Automatic placing, 13 percent less spreading

Four modes, uninterrupted placing

It switches between automatic, follow-up, jog and manual modes; placing continues whether power, staff or site conditions change.

  • The machine is operated directly by traditional workers.

Ten safety designs, three times the life

Ten safety designs raise the safety of the placing process; the whole structure has passed simulation and field testing, with a main structure life above 3 years.

  • It works in 13.8 m/s wind.

The BMR Takipli Beton Dağıtım Bomu 12-20 m up close

2 images; tap to enlarge.

Technical Specifications

10 values in 6 categories; data published by the manufacturer.

General structure
Materials
Steel structure passed simulation and field testing; main structure life ≥3 years; ten safety designs
Manufacturer note
Four operation modes: automatic (placing on a preset path), follow-up (single-person joystick operation), remote (remote operation of boom and arm) and manual (traditional manual pulling).
Size and weight
Dimensions (standing)
Outrigger span 3.6 × 3.6 m (12 m) / 4.2 × 4.2 m (15 m); reserved opening 1.2 × 1.2 to 1.5 × 1.5 m or lift shaft 2.1 × 2.1 to 2.3 × 2.3 m (18 and 20 m)
Weight
1600 / 1700 / 3100 / 3300 kg (12 / 15 / 18 / 20 m, excluding counterweight)
Motion and performance
Work capacity
Maximum placing radius 12 / 15 / 18 / 20 m; minimum weight for floor-to-floor transfer 1.6-1.7 t (2.2 t) / 2.2 t / 2.5 t; maximum wind 13.8 m/s (force 6)
Power and runtime
Battery
Three-phase five-wire AC 380 V (±40 V) mains supply
Sensors and connectivity
Sensors
Boom position and route sensing; ten safety designs
Interfaces
Hand controller and remote control; direct operation by traditional workers
Software and development
Processor
Follow-up control managing the main and fly booms by algorithm; automatic placing along a preset route
Software features
Four modes: automatic (preset route), follow-up (single-person hand controller), jog (remote control), manual; automatic slab placing without BIM

Sources and documents

Verified on the manufacturer page on 18 September 2026.

An itemised quote for the BMR Takipli Beton Dağıtım Bomu 12-20 m is prepared by configuration, quantity and delivery scope.

Follow-Up Concrete Placing Boom: Technical AnalysisDesign decisions, comparison table and evaluation

From a placing crew to a single operator

The crew pulling the hose and boom on slab concrete is at least three people; the boom's movement depends on muscle and experience, and when placing is uneven the levelling crew spreads extra. The Follow-Up Concrete Placing Boom manages the boom and arm by algorithm: in follow-up mode one person carries the hand controller, the arm follows them and 30 percent of the traditional labour suffices. In automatic mode it places along a preset route by itself; uniform placing cuts levelling work by 13 percent and, together with a high-precision slab, slab cost falls by about 28 percent.

Four sizes, two installation methods

The HG12 and HG15 (1.6 and 1.7 t) sit on the slab with 3.6 × 3.6 and 4.2 × 4.2 m outrigger spans and move between floors at 1.6-1.7 t (2.2 t); they are chosen for residential tower floors. The HG18 and HG20 (3.1 and 3.3 t) are installed in a reserved slab opening of 1.2 × 1.2 to 1.5 × 1.5 m or in a lift shaft of 2.1 × 2.1 to 2.3 × 2.3 m; they are chosen for wide basement and factory slabs. All four run on three-phase five-wire AC 380 V (±40 V) and withstand 13.8 m/s (force 6) wind.

Four operating modes

  • Automatic mode: automatic placing along a preset route; no BIM data needed.
  • Follow-up mode: single-person hand controller, the arm follows the operator.
  • Jog mode: the main and fly booms driven by remote control.
  • Manual mode: traditional manual pulling; placing continues whether power or site conditions change.

Figures from the field

  • Shenzhen Semiconductor and Advanced Manufacturing Industrial Park (China Construction Third Engineering Bureau, 278,000 m²): synchronised placing and levelling with the follow-up boom and the 2.5 m levelling robot; one operator, the workforce down by 4 people (40 percent), consistent millimetre-level quality.
  • Asia-Pacific Headquarters of CanSino Clinical Research and Operations, Guangzhou (China Nuclear Industry Huaxing Construction, 47,988 m²): the integrated concrete robot set cut the workforce by 40 percent.
  • Foshan Fengtong Garden (February 2021, a Ministry intelligent-construction pilot project): more than 20 construction robots in auxiliary, concrete structure and decoration works; two practices entered the Ministry's list of replicable practices.

Who it is for

For general contractors and concrete pump operators pouring floor slabs and basements; together with the Concrete Leveling Robot and the 80SZ Trowelling Robot one crew covers pour to polish. The placing radius is chosen by the farthest corner of the floor plan.

Price and sourcing

The Takipli Beton Dağıtım Bomu is sourced for Turkey on a project basis; import, customs clearance, commissioning and operator training are part of delivery. Investment is set by corporate quotation against edition, configuration, spare and wear-part provisioning, training scope and quantity. The installation method (outriggers, slab opening or lift shaft) and the floor plan are stated in the quotation. Request a quotation with your project profile.

Follow-Up Concrete Placing Boom Technical Specifications

ParameterHG12 | HG15 | HG18 | HG20
Maximum placing radius12 m | 15 m | 18 m | 20 m
Total weight (excluding counterweight)1.6 t | 1.7 t | 3.1 t | 3.3 t
Minimum weight for transfer between floors1.6 t (2.2 t) | 1.7 t (2.2 t) | 2.2 t | 2.5 t
Installation dimensionsOutrigger span 3.6 × 3.6 m | Outrigger span 4.2 × 4.2 m | Preformed hole 1.2 × 1.2 to 1.5 × 1.5 m or lift shaft 2.1 × 2.1 to 2.3 × 2.3 m (HG18, HG20)
Operating voltageAC 380 V (±40 V), three-phase five-wire
Product functionsAutomatic (preset path), follow-up (single-person joystick), remote (boom and arm), manual (traditional pulling)
Maximum wind resistance13.8 m/s (force 6 wind)
Main structure life≥3 years; ten safety designs

Summary

The Follow-Up Concrete Placing Boom brings slab concrete placing from a three-person hose crew down to one operator: a 12-20 m radius, an arm that follows the operator, automatic placing along a preset route, four modes and 380 V mains supply. At the 278,000 m² industrial park in Shenzhen and the CanSino headquarters in Guangzhou it cut the workforce by 40 percent together with the levelling robot. For contractors wanting pour, levelling and trowelling from one crew on floor slabs and basements, request a quotation with your floor plan.

Purchasing support

Get a quote for the Takipli Beton Dağıtım Bomu 12-20 m

Robotic system costs are optimised according to the selected hardware platform, additional sensor and payload configurations, and the integration scenarios specific to your site. Share your requirements and our engineering team will prepare a feasibility report and a pro forma quotation tailored to your organisation.

  • Supply and delivery scheduling backed directly by the manufacturer
  • Site- and mission-focused technical feasibility and simulation
  • Turnkey hardware, software and mission integration
  • Advisory on corporate tenders, specifications and administrative processes

Direct contact and advisory line: 0850 532 6 777

Add project details (optional)

Product of interest: Takipli Beton Dağıtım Bomu 12-20 m

Takipli Beton Dağıtım Bomu 12-20 m: Frequently Asked Questions

The most common questions about the BMR Takipli Beton Dağıtım Bomu 12-20 m.

Which radius should be chosen?

12, 15, 18 or 20 m is chosen by the farthest corner of the floor plan. The HG12 and HG15 sit on the slab with 3.6 × 3.6 and 4.2 × 4.2 m outrigger spans and move easily between floors at 1.6-1.7 t; the HG18 and HG20 are installed in a slab opening or lift shaft.

Does automatic mode need BIM?

No. Automatic slab placing runs along a preset route and needs no BIM data; the machine is operated directly by traditional workers. In follow-up mode one person carries the hand controller and the arm follows them.

What electrical infrastructure is required?

A three-phase five-wire AC 380 V (±40 V) supply is required, fed from the site distribution board. Maximum wind resistance is 13.8 m/s.

Is it used together with the levelling robot?

Yes. At the Shenzhen semiconductor park the follow-up boom and the 2.5 m Concrete Leveling Robot worked in step and one operator managed placing; uniform placing cuts levelling work by 13 percent. The 80SZ Trowelling Robot then finishes the surface.

How is it sourced in Turkey?

The BMR Takipli Beton Dağıtım Bomu is sourced on a project basis: the site schedule, floor area, concrete or coating system and site access are settled at the survey; import, commissioning and operator training are part of delivery. For a quotation, send the project type, total square metres and the works programme.