A boom that follows the operator
In follow-up mode the main and fly booms are managed by algorithm; one person drives the placing with a hand controller and 30 percent of the traditional labour suffices.
- Two placing workers are saved.

Intelligent Follow-Up Concrete Placing Boom
The BMR Intelligent Follow-Up Concrete Placing Boom is a construction machine that places concrete on floor slabs and in basements at a 12, 15, 18 or 20 metre radius, managing the boom movements by algorithm.
In follow-up mode a single-person hand controller needs 30 percent of the traditional labour; in automatic mode it places along a preset route by itself and cuts spreading work by 13 percent. It switches between four modes, automatic, follow-up, jog and manual, runs on 380 V three-phase power and withstands 13.8 m/s wind.
Enterprise supply · specification support · integration engineering
The Follow-Up Concrete Placing Boom mechanises the distribution of slab concrete over the formwork and comes in four sizes by placing radius: 12, 15, 18 and 20 metres. Machine weight excluding counterweight is 1.6 t at 12 m, 1.7 t at 15 m, 3.1 t at 18 m and 3.3 t at 20 m; the minimum weight for floor-to-floor transfer is 1.6-1.7 t (2.2 t) at 12 and 15 m, 2.2 t at 18 m and 2.5 t at 20 m. The 12 and 15 m editions sit on the slab with 3.6 × 3.6 and 4.2 × 4.2 m outrigger spans; the 18 and 20 m editions are installed in a reserved slab opening of 1.2 × 1.2 to 1.5 × 1.5 m or in a lift shaft of 2.1 × 2.1 to 2.3 × 2.3 m.
There are four operating modes: automatic mode placing along a preset route by itself, follow-up mode run by one person with a hand controller, jog mode where the main and fly booms are driven by remote control, and traditional manual pulling; placing continues whatever the conditions. Follow-up placing saves two placing workers and automatic placing one more levelling worker; the high uniformity of automatic placing cuts spreading work by 13 percent, and together with a high-precision slab the slab cost falls by about 28 percent. The machine is operated directly by traditional workers; automatic slab placing needs no BIM data. Ten safety designs raise the safety of the placing process; the whole structure has passed simulation and field testing, with a main structure life above 3 years. Working voltage is three-phase five-wire AC 380 V (±40 V) and maximum wind resistance 13.8 m/s (force 6). References: at the Shenzhen Semiconductor and Advanced Manufacturing Industrial Park (278,000 m², China Construction Third Engineering Bureau) the follow-up boom worked in step with the 2.5 m levelling robot, one operator managed placing and the workforce fell by 4 people (40 percent); at the Asia-Pacific Headquarters of CanSino Clinical Research in Guangzhou (47,988 m²) the same set cut the workforce by 40 percent; Foshan Fengtong Garden, one of the first intelligent-construction pilot projects of China's Ministry of Housing and Urban-Rural Development, was built with more than 20 construction robots.
In follow-up mode the main and fly booms are managed by algorithm; one person drives the placing with a hand controller and 30 percent of the traditional labour suffices.

In automatic mode the boom places along a preset route by itself; high uniformity cuts spreading work by 13 percent and frees one more levelling worker.

It switches between automatic, follow-up, jog and manual modes; placing continues whether power, staff or site conditions change.
Ten safety designs raise the safety of the placing process; the whole structure has passed simulation and field testing, with a main structure life above 3 years.
2 images; tap to enlarge.
10 values in 6 categories; data published by the manufacturer.
Verified on the manufacturer page on 18 September 2026.
An itemised quote for the BMR Takipli Beton Dağıtım Bomu 12-20 m is prepared by configuration, quantity and delivery scope.
The crew pulling the hose and boom on slab concrete is at least three people; the boom's movement depends on muscle and experience, and when placing is uneven the levelling crew spreads extra. The Follow-Up Concrete Placing Boom manages the boom and arm by algorithm: in follow-up mode one person carries the hand controller, the arm follows them and 30 percent of the traditional labour suffices. In automatic mode it places along a preset route by itself; uniform placing cuts levelling work by 13 percent and, together with a high-precision slab, slab cost falls by about 28 percent.
The HG12 and HG15 (1.6 and 1.7 t) sit on the slab with 3.6 × 3.6 and 4.2 × 4.2 m outrigger spans and move between floors at 1.6-1.7 t (2.2 t); they are chosen for residential tower floors. The HG18 and HG20 (3.1 and 3.3 t) are installed in a reserved slab opening of 1.2 × 1.2 to 1.5 × 1.5 m or in a lift shaft of 2.1 × 2.1 to 2.3 × 2.3 m; they are chosen for wide basement and factory slabs. All four run on three-phase five-wire AC 380 V (±40 V) and withstand 13.8 m/s (force 6) wind.
For general contractors and concrete pump operators pouring floor slabs and basements; together with the Concrete Leveling Robot and the 80SZ Trowelling Robot one crew covers pour to polish. The placing radius is chosen by the farthest corner of the floor plan.
The Takipli Beton Dağıtım Bomu is sourced for Turkey on a project basis; import, customs clearance, commissioning and operator training are part of delivery. Investment is set by corporate quotation against edition, configuration, spare and wear-part provisioning, training scope and quantity. The installation method (outriggers, slab opening or lift shaft) and the floor plan are stated in the quotation. Request a quotation with your project profile.
| Parameter | HG12 | HG15 | HG18 | HG20 |
|---|---|
| Maximum placing radius | 12 m | 15 m | 18 m | 20 m |
| Total weight (excluding counterweight) | 1.6 t | 1.7 t | 3.1 t | 3.3 t |
| Minimum weight for transfer between floors | 1.6 t (2.2 t) | 1.7 t (2.2 t) | 2.2 t | 2.5 t |
| Installation dimensions | Outrigger span 3.6 × 3.6 m | Outrigger span 4.2 × 4.2 m | Preformed hole 1.2 × 1.2 to 1.5 × 1.5 m or lift shaft 2.1 × 2.1 to 2.3 × 2.3 m (HG18, HG20) |
| Operating voltage | AC 380 V (±40 V), three-phase five-wire |
| Product functions | Automatic (preset path), follow-up (single-person joystick), remote (boom and arm), manual (traditional pulling) |
| Maximum wind resistance | 13.8 m/s (force 6 wind) |
| Main structure life | ≥3 years; ten safety designs |
The Follow-Up Concrete Placing Boom brings slab concrete placing from a three-person hose crew down to one operator: a 12-20 m radius, an arm that follows the operator, automatic placing along a preset route, four modes and 380 V mains supply. At the 278,000 m² industrial park in Shenzhen and the CanSino headquarters in Guangzhou it cut the workforce by 40 percent together with the levelling robot. For contractors wanting pour, levelling and trowelling from one crew on floor slabs and basements, request a quotation with your floor plan.
Supply model
Supply to Turkey is planned per project; import, delivery and commissioning scope are itemised in the quote.
Pre-sales assessment
Site and mission focused technical feasibility; specification and administrative process support.
Demo and site visit request
Send a demo request; availability and scope are settled in the call.
Source documents
Technical values come from the manufacturer's documents; verified on 18 September 2026. 0 documents at the bottom of the page.
Robotic system costs are optimised according to the selected hardware platform, additional sensor and payload configurations, and the integration scenarios specific to your site. Share your requirements and our engineering team will prepare a feasibility report and a pro forma quotation tailored to your organisation.
Direct contact and advisory line: 0850 532 6 777
The most common questions about the BMR Takipli Beton Dağıtım Bomu 12-20 m.
12, 15, 18 or 20 m is chosen by the farthest corner of the floor plan. The HG12 and HG15 sit on the slab with 3.6 × 3.6 and 4.2 × 4.2 m outrigger spans and move easily between floors at 1.6-1.7 t; the HG18 and HG20 are installed in a slab opening or lift shaft.
No. Automatic slab placing runs along a preset route and needs no BIM data; the machine is operated directly by traditional workers. In follow-up mode one person carries the hand controller and the arm follows them.
A three-phase five-wire AC 380 V (±40 V) supply is required, fed from the site distribution board. Maximum wind resistance is 13.8 m/s.
Yes. At the Shenzhen semiconductor park the follow-up boom and the 2.5 m Concrete Leveling Robot worked in step and one operator managed placing; uniform placing cuts levelling work by 13 percent. The 80SZ Trowelling Robot then finishes the surface.
The BMR Takipli Beton Dağıtım Bomu is sourced on a project basis: the site schedule, floor area, concrete or coating system and site access are settled at the survey; import, commissioning and operator training are part of delivery. For a quotation, send the project type, total square metres and the works programme.