Container Yard Surface Damage and Deformation Detection
Scenario record: it defines the environment, the mission flow and a proposed hardware and software configuration. The list below is a configuration proposal, not an installation inventory. Field projects lists deployed systems and their measurements.
- Environment
- Outdoor field
- Operating mode
- Supervised autonomy
- Proposed robot
- Unitree B2-W
The problem addressed
Manually inspecting thousands of containers for damage is impossible, leading to costly liability disputes over when damage occurred.
Draft mission flow
- 1Robot liman konteyner depolama sahasında satır aralarında devriye atarak konteynerlerin dış yüzeyini kameralarla tarar.
- 2Çentik, delinme, korozyon ve köşe bağlantı eğrilmesi gibi fiziksel hasarlar 3D LiDAR ve görsel analizle tespit edilir.
- 3OCR ile konteyner numarası okunarak hasar verisi ilgili konteynerle eşleştirilir; sigorta talebi için kanıt oluşturulur.
- 4Limana giriş/çıkışta otomatik hasar envanteriyle söz konusu hasarın ne zaman oluştuğu sorumluluk zinciri belgelenir.
Proposed hardware
- HD Kamera
- 3D LiDAR
- Termal Kamera
- ANPR Modülü
- Konteyner Numarası OCR
Proposed software
- Navigation
- Konteyner blok satırları arasında kafes yolu koridorlarında otonom devriye
- Model
- Konteyner Gövde Çentik/Delinme Tespiti, Köşe Bağlantısı Deformasyon Analizi ve Sızdırmazlık Riski Puanlama
- Integration
- Liman Terminal İşletme Sistemi (TOS) ve Konteyner Sigorta Veri Tabanı
The robot's real operating limits

Unitree B2-W
Wheeled industrial robot dog: IP67
Product page- Ingress rating
- IP67
- Operating temperature
- -20°C to 55°C
- Payload
- 120 kg
- Max speed
- 15
- Climb
- 45°
- Weight
- 85 kg
Values are manufacturer data. Scenario fit is determined by comparing these limits with site conditions.
From scenario to installation
Feasibility is determined by the site survey: floor and route, network coverage, the charging point, intervention responsibilities and the conditions under which the robot must stop. The survey report defines the scope, the constraints and the commissioning steps.