Skip to content
Robotlar
Concept scenario

Textile Mill Dust and Lint Buildup Fire Risk Detection

Scenario record: it defines the environment, the mission flow and a proposed hardware and software configuration. The list below is a configuration proposal, not an installation inventory. Field projects lists deployed systems and their measurements.

Environment
Outdoor field
Operating mode
Teleoperation
Proposed robot
Unitree A2

The problem addressed

Dust and lint buildup combined with static sparks: the most common cause of textile factory fires in Turkey.

Draft mission flow

  1. 1Robot tekstil üretim salonlarını dolaşarak havadaki toz/lif yoğunluğunu lazer partikül ölçerle sürekli izler.
  2. 2Tezgah altı, havalandırma kanalı ağzı ve elektrik panosu çevresindeki birikmiş lif yığınları kamerayla tespit edilir.
  3. 3Termal kamerayla aşırı ısınan motor, rulman ve elektrik bağlantıları raporlanır; yangın başlangıç riski puanlanır.
  4. 4Yangın riski yüksek bölgeler acil temizlik iş emriyle fabrika İSG birimine bildirilir.

Proposed hardware

  • Lazer Partikül Ölçer
  • HD Kamera
  • Termal Kamera
  • Nem/Sıcaklık Sensörü
  • Anti-Statik Pedler

Proposed software

Navigation
Tekstil üretim hattı, iplik-dokuma salonları ve havalandırma kanalları arası otonom devriye
Model
Toz/Lif Yoğunluk Haritası, Statik Elektrik Yükü Risk Segmentasyonu ve Tezgah Aşırı Isınma Tespiti
Integration
Fabrika Yangın Güvenlik Sistemi ve İSG Yönetim Platformu

The robot's real operating limits

Unitree A2

Unitree A2

Industrial robot dog: 100 kg static payload

Product page
Ingress rating
IP56-IP67
Runtime
>5 hours (No load) / >3 hours (25kg Load)
Operating temperature
-20°C to 55°C
Payload
100 kg
Max speed
5 m/s
Climb
45°

Values are manufacturer data. Scenario fit is determined by comparing these limits with site conditions.

From scenario to installation

Feasibility is determined by the site survey: floor and route, network coverage, the charging point, intervention responsibilities and the conditions under which the robot must stop. The survey report defines the scope, the constraints and the commissioning steps.